The Newberg Graphic, Newberg Oregon Contact | Site Map | Subscribe | Home

www.NewbergGraphic.com

 


 

 

 

 

 

 

 

 
nv-realestate.gif (1249 bytes)

Nv-contact.gif (1489 bytes)

Nv-advertise.gif (1492 bytes)

Archive

Subscribe

Weather



Hess firing based in part on racial slur

McUpdate: Rebuilding effort could begin in weeks

Foe of North Newberg LID wants to scrap the entire system

Catching up on construction

The flurry of activity at Mabel Rush and Ewing Young elementaries, as well as NHS, on schedule

By Schellene Clendenin, Newberg Graphic reporter
E-mail Schellene at sclendenin@eaglenewspapers.com
   Not long after kids moved out of their classrooms at Mabel Rush and Ewing Young elementary schools in June, construction crews went to work. At first the schools looked like they were part of a demolition exercise rather than a renovation effort.
   In a scene reminiscent of the destruction wrought by a tornado, walls and ceilings, floor tiles and entire sections of Mabel Rush were pulled down, said Paul Frankenburger, director of physical and plant services for the school district.
   “It’ll be a while before it gets healed,” he said.
   Renovation on the 45-year-old 53,700 square foot school will include adding classrooms, a cafeteria and media center; adding space for kindergarten and music classrooms and an expanded parking and parent pick-up area.
   Included in the renovations inherent in Bid Package 3, Mabel Rush and Ewing Young elementary schools and Mountain View Middle School is the installation of security systems, according to Claudia Stewart, communications specialist for the school district.
   Construction crews are in the midst of demolition and underground work and plumbing at Mabel Rush, Frankenburger said. “They’ve formed and poured the foundation for an addition and excavated and placed the base rock for the driveway.”
   Corridor ceilings were removed in order to raise them and accommodate duct work and plumbing, as well as opening up the area to allow more daylight into the building.
   “The ceilings were too low with no place for mechanical chase duct work and plumbing, so we created one,” Frankenburger said, adding that asbestos removal is nearly complete, although there may be some incidental asbestos found in pockets of the building.
   Licensed environmental contractors removed and are still removing floor tiles containing asbestos at Mabel Rush, Stewart said in an e-mail. Some of this work was done last summer in anticipation of construction start. The contractor should be done with the asbestos removal in approximately one week.
   Adding to the appearance of destruction to Mabel Rush is the removal of bathrooms, the cafeteria, the front entryway, windows, some of the walls and big pieces of the roof, Frankenburger said. “There were a lot of things wrong with (the building),” he said.
   The plumbing in the building was in poor shape, he maintained: much of it was underground and had deteriorated to the degree that it had to replaced. Insulation will also be installed. Prior to the renovation there was little insulation except for in the roof.
   There will be some fairly large additions to the school, including a new media center placed in an area that formerly was the courtyard, and enlarging the cafeteria.
Construction is on schedule, Stewart said, and should be completed by April 2005.
   The amount meted to Mabel Rush from a $46.3 million bond passed by voters in 2002 is more than $5.6 million. Bid Package 3, which includes improvements to Ewing Young Elementary and Mountain View Middle schools totals slightly more than $8 million.
   The dust has yet to settle at Ewing Young Elementary.
   “Contractors are cutting skylights in the roof and have demolished big portions of the office,” Frankenburger said.
   The foundation and slabs except for the main entry have also been poured, he added. Crews are focusing on the interior renovation portion of the project. The district set aside more than $1.8 million for the renovation in the bond.
   Contractors will renovate the 22,557-square-foot school, add kindergarten and music classrooms, replace flooring, construct a new well, modify or expand the existing sand filter and septic systems, add parking and revise the bus pick-up area, Stewart said.
   Renovation is on schedule, she added, and should be completed in August. The addition is slated to be in place by January 2005.
   Also a part of Bid Package 3, MVMS is on schedule and doing well, Frankenburger said. Heating, ventilation and air conditioning modules (HVAC) are the most complicated aspect of renovation at the school and the work is well underway.
   Currently contractors are working on the mechanical system, framing and flooring at the school. Work will include interior renovation for additional storage, a staff work area and student health room, installation of a chiller and addition of chilled water coils to existing fans, cleaning and resealing the brick exterior and new floor finishes included in the more than $600,000 bid price.
    Construction should be complete at the middle school this month, Stewart added, and mechanical improvements in September.

From Aug. 7, 2004, Newberg Graphic
Click Here to Subscribe

 

 
SPONSORS:




 


newbergallery-rotation.gif (6174 bytes)



 

Copyright 2004 Newberg Graphic, Newberg Oregon
Contact us with your questions or comments about the site.
This site is best viewed with
Microsoft Internet Explorer 5.0+